Kitchen reconfiguration and two full bathrooms — cabinetry, quartz, waterproofing rebuild, and finishes coordinated across both floors.
Scope
A West Island family home pulled into a single coordinated phase: kitchen reconfiguration plus two full bathrooms. The plumbing re-route on the primary ensuite alone took a week — original drains were under a slab pour and required a small saw-cut to bring the new drains to grade.
Highlights
- Custom shaker cabinetry with brushed nickel hardware
- Quartz counters with seamless undermount sinks
- Schluter-Kerdi waterproofing on all three wet floors
- Niche storage built into framed walls
- Heated tile flooring in the primary ensuite
Notes
Sequencing two baths and a kitchen on the same site let us share trades across the day — the same tiler ran all three wet rooms over five consecutive days, which kept the schedule tight and the finish consistent.